Order a Desktop Structural Report → Free Structural Pre-Check Tool →

IRELAND / TAMS REROOFING / S101R

TAMS reroofing: the Chartered Engineer's report

Where a farm building is reroofed and the existing stanchions or rafters are kept, specification S101R requires a Chartered Engineer's report, submitted with the initial application for grant aid. We survey the frame, write the report to the S101R list and send it signed, with the documents the Department asks for.

Steel rafters and purlins under an older corrugated sheet roof with rooflights, seen from inside
S101RReport written to section 3
15yrMinimum expected life of retained members
24hrTarget for quotes
£5MProfessional Indemnity
£5M PROFESSIONAL INDEMNITY
BDF + BMFA ACCREDITED PILOTS
EUROCODE VERIFIED
ENGINEERING PRINCIPALS 20+ YEARS
ACE & EIC MEMBER

THE CHARTERED ENGINEER'S REPORT FOR TAMS REROOFING

Grant aided reroofing of farm buildings is done to the Department of Agriculture, Food and the Marine's specification S101R, Minimum Specification for Reroofing Farm Buildings. Section 3 of S101R requires a Chartered Engineer's report wherever the stanchions or rafters are proposed not to be replaced. The report records the condition and dimensions of every retained member, the dimensions of the building, the cleats, the connections and their bolts and nuts, and the expected life of what is kept, which must be at least 15 years. It goes in with the initial application for grant aid. The Department decides every application; the report gives it the information S101R asks for.

Source: S101R, Minimum Specification for Reroofing Farm Buildings, Department of Agriculture, Food and the Marine, December 2025 (PDF).

WHEN THE REPORT IS NEEDED

When S101R asks for a Chartered Engineer

The report is required where the stanchions or rafters are to be kept rather than replaced (section 3). If any kept member does not meet specification S101, a full set of design calculations goes with the report.

Where the building is outside S101 on eaves height, roof slope or span, the Department wants a full set of design drawings, with steel sizes and joint details, and full structural calculations for the entire building, prepared by a Chartered Engineer to IS EN 1993 and any other relevant Eurocode, for its approval before construction starts (section 6.8).

Where a different design is proposed for any element in the specification, S101R asks for a full rationale and full design details, including structural design calculations by a Chartered Engineer where relevant, submitted for the Department's acceptance before any works start.

WHERE S101R NEEDS A CHARTERED ENGINEER

  • Stanchions or rafters kept rather than replaced (section 3)
  • Kept members that do not meet S101: design calculations with the report (section 3)
  • A building outside S101 on eaves height, roof slope or span (section 6.8)
  • A different design proposed for any element (the specification's opening notes)

WHAT THE REPORT COVERS

Written to the list in section 3

Section 3 of S101R sets out what the report must contain. We survey the frame and write the report to that list, so each item can be checked against the specification.

The expected life decides most cases. S101R sets a minimum expected life of 15 years for any stanchion or rafter that stays. Where that cannot be verified, the member must be replaced. The report says which members can stay and which cannot.

Stanchions cannot be extended. If the reroofed building needs to be taller, S101R requires full new stanchions, including foundations.

S101R SECTION 3

  • A detailed condition survey of every stanchion and rafter being kept
  • The length, width and breadth of each one
  • The building's span, bay widths, eaves height, apex height and roof gradient
  • The condition of all cleats on the stanchions and rafters being kept
  • Where rafters are kept: every connection, with the size and condition of the bolts and nuts
  • The expected life of the members being kept, at least 15 years
  • Where kept members do not meet S101: design calculations for the span, bay widths, eaves height and any other load that will go on them

WHO SIGNS, AND WHAT WE SEND

The Department of Agriculture, Food and the Marine confirmed in writing in November 2026 that the Chartered Engineer may be registered with Engineers Ireland or with the Engineering Council in the UK. Where the engineer is registered with the Engineering Council, proof of registration and a copy of professional indemnity insurance go with each report. Our reports are signed by a Chartered Engineer registered with the Engineering Council, and we send both documents with every report.

ROOF ACCESS

Every roof treated as fragile

S101R says to treat every roof as fragile unless a competent person confirms otherwise, and to follow the HSA Code of Practice for Safety in Roofwork. We go onto a roof only when proper safety measures are in place; otherwise we inspect the frame from inside and from safe access. The covering, rooflights and gutters can be recorded by drone, with nobody on the sheet.

OUTSIDE THE REPORT

  • Taking down or disposing of the existing structure: not grant aided under S101R, and carried out following Health and Safety Authority guidance (section 2)
  • Full planning permission or a declaration of exemption specifically for the reroofing; the original one for the building is not sufficient (section 4)
  • Cleaning retained stanchions and rafters of rust and painting them with at least two coats of micaceous iron oxide finishing coat, as part of the works (sections 6.2 and 6.3)

SOLAR ON THE NEW ROOF

Planning panels on the new roof?

If panels are planned for the new roof, tell us at quote and we check the frame for the panel load as well. See structural surveys for solar panels in Ireland.

ENGINEERING SERVICES IN IRELAND

Our other services

Each service stands alone or combines with the TAMS report under one instruction.

ON-SITE STRUCTURAL SURVEY

A qualified structural engineer measures the frame, purlins, spans and fixings on site and checks them against the proposed array. The route for undocumented buildings, older roofs and anything a funder or insurer will look at closely.

On-site structural surveys →

DRONE ROOF CONDITION ASSESSMENT

The condition of the covering, rooflights, gutters and flashings recorded from the air, with nobody on the sheet. On a fragile roof it is the safe way to see the covering.

Drone roof condition surveys →

DESKTOP STRUCTURAL ROOF LOADING REPORT

Where drawings, photographs and measurements are available, the roof is appraised remotely by the same Eurocode method. Used to screen an estate before deciding where to survey.

Desktop reports →

DRONE TECHNICAL SURVEY

A qualitative inspection of solar PV sites and industrial structures from the air, reviewed by an engineer, without scaffold.

Drone technical surveys →

STRENGTHENING DESIGN

Where a roof falls short, we design the strengthening, with calculations and drawings a contractor can build from, and we inspect the finished work.

Structural engineering for solar PV →

ROOF REFURBISHMENT AND OVERCLADDING

Structural appraisal and design for reroofing, overcladding and strengthening older industrial and agricultural buildings, with or without solar PV.

Roof refurbishment engineering →

HOW IT WORKS

From photographs to a signed report

STEP 1

Send the details

The farm address, photographs of the roof and of the frame inside, and any drawings.

STEP 2

Priced quote

We aim to send a priced quote within 24 hours of receiving them.

STEP 3

Site survey

We survey the frame, with the programme agreed at quote.

STEP 4

The signed report

Sent with proof of Engineering Council registration and our professional indemnity certificate, ready to go in with the application.

FREQUENTLY ASKED QUESTIONS

Questions about the TAMS reroofing report

Do I need a Chartered Engineer's report for TAMS reroofing?+

Where the stanchions or rafters are being kept, yes: S101R section 3. If every stanchion and rafter is being replaced and the building is within S101, section 3 does not ask for one.

When does the report go in?+

With the initial application for grant aid. S101R section 3 says so.

Can a UK registered Chartered Engineer sign it?+

Yes. The Department of Agriculture, Food and the Marine confirmed in writing in November 2026 that the engineer may be registered with the Engineering Council in the UK, with proof of registration and a copy of professional indemnity insurance sent with each report. We send both.

What if the frame will not reach 15 years?+

S101R requires those stanchions or rafters to be replaced. The report says which members can stay and which cannot.

My shed is outside S101 on eaves height, roof slope or span. Can it still be reroofed?+

S101R section 6.8 allows it, with a full set of design drawings, including steel sizes and joint details, and full structural calculations for the entire building, prepared by a Chartered Engineer and given to the Department for prior approval before construction starts. We prepare those.

TAMS REROOFING IN IRELAND

Ready to Proceed?

Send us the farm address, photographs of the roof and of the frame inside, and any drawings. We aim to return a priced quote within 24 hours.

GLOSSARY
LOCATIONS